Windsor Road Project Update 8.1.2023
Good afternoon,

The contractor for Windsor Road is working on trail grading. Curb and gutter should be installed the end of this week or early next week (8/7).

Tomorrow, August 2nd, Conservancy Plaza will be down to one lane to install a sanitary sewer manhole. The work will take place between 8 am to 4 pm. There will be flaggers on site to get traffic through, so there shouldn’t be any delays. Please use caution when traveling through this area and watch for workers. The above map identifies the location of the work.

If you have any questions please reach out, 608-807-7023.

Greg



Greg Hall
Public Services Operations Supervisor
Village of DeForest
608-807-7023
DeForest, Wisconsin