Windsor Road Project Update 8.11.2023
Good morning,

Thank you for your patience on this project! Curb and gutter will be getting installed starting Tuesday, August 15th. Residents on Windsor Road will need to park temporarily on Highland Drive or Sunfish Pond parking lot, while the concrete is poured and cures. Once the concrete is poured, you will be able to park in front of your home until the concrete is cured, roughly 3-5 days. The contractor will get you into your driveway once the concrete has cured.

Next step will be finish grading the road to prepare for asphalt.

The bridge project has finished and will be ready for asphalt when we pave the rest of Windsor Road.

If you have any questions or concerns, please give me a call 608-807-7023 or email.

Greg



Greg Hall
Public Services Operations Supervisor
Village of DeForest
608-807-7023
DeForest, Wisconsin
Village Hall
120 S. Stevenson Street
DeForest, WI 53532
(608) 846-6751
Growing the Good Life