Good Morning,
We are getting closer to the end of the Windsor Road reconstruction project. The rest of the curb and gutter will be installed this week and finish grading will be completed as well. Starting September 6th the contractor will be paving Windsor Road. The plan is to have it completed by the end of the week. During the paving operations, there may be small delays getting into your homes, but once the pavement has been rolled the contractor will let you in. If you live on Windsor Road it may be a good idea to park at Sunfish Pond for a couple days while they are paving and you need to get out. Otherwise, you will have access most of the day.
Once the paving is complete, we still have some work to complete like restoration of the terraces, tree plantings and pavement markings. Once this is all completed we will then open the road up to traffic. Thank you for your patience during this project and if you have any questions please feel free to contact me.