The Wallbrook (Publix) project started the blasting phase last week. Seismographs will be used to measure ground vibration and airblast levels. The schedule is below.
Blasting will be Monday - Friday starting next Tuesday, February 20, 2024.
· 1st blast – between 10:00am & 12:00pm
· 2nd blast – between 1:00pm & 3:00pm
The times might be adjusted due to inclement weather. Depending on ground conditions on the job site blasting times and schedules may change. Before each blast a siren or air horn will sound, no blasting will be conducted on weekends or State/Federal holidays.
If you have any questions, please contact the blasting company at cdbquestions@civilblasting.com
|