To close out the latest phase of the Con Edison gas main work, Con Edison's contractor will be paving roads in Miller Park and Crest Neighborhoods next week and the following.
The following is a more detailed schedule than provided previously to assist homeowners that may need to find parking on nearby streets while their road is being paved:
-
Monday and Tuesday, July 15 and 16: Mill and pave Bridge Street, MacArthur Lane, and Riverview Avenue.
-
Wednesday and Thursday, July 17 and 18: Mill and pave Miller Avenue, Glen Street, and Independence Street.
-
Friday and Monday, July 19 and 22: Mill and pave Midland Avenue, Ridgewood Terrace and Barnes Road.
Parking permit restrictions will be waived for these two neighborhoods during this paving project so that residents can seek parking on nearby streets. Please follow posted No Parking Signs which will indicate the specific times and dates of milling and paving on each street. Vehicles parked in violation may be subject to towing.
Please reach out to the Village Administrator's office with any questions: (914) 631-1785 or administrator@tarrytownny.gov
|