County Ave Water Main Project –
Bid Opening was held June 6th and the Township Council awarded the project to Booth Mechanical in the amount of $291,832.50 for necessary improvements to the water system infrastructure.
North Cedar Ave and 500 Block of Alexander Ave Miscellaneous Roadway Restoration Project –
Contract Awarded to Think Pavers Hardscaping LLC in the amount of $127,251.00. Work to begin on or about August 12th (weather permitting)
Waste Water Screw Pump Refurbishment Project –
In Progress. First of 2 Screw Pumps Installed on 08/06/2024, with manufacturer’s visit scheduled for week of 08/12/2024.
Windsor Pump Station Force Main By-Pass –
Award of project to Booth Mechanical in the amount of $32,710.00. Work began in early July.
County Ave Roadway Repair –
Currently under investigation
N. Terrace Ave Roadway Repair –
Currently under investigation
Rose Ave Water Main Replacement Project –
Design in Progress
Forklanding Road and Yocum School Pedestrian Improvements –
In Engineering Design
Kings Highway Water Treatment Plant –
Formal Agreement to purchase land parcel is in progress. Township has received $850,000 grant to help offset costs of replacing the well house structures and adding a water storage tank to the site.
|