Project Progress: The first construction season (2022) focused on the installation of underground utilities (water, sewer, electric and communication duct bank) and stormwater infrastructure between Home Avenue and Sears Lane, and the sand filter installed the Miller Building on Lakeside Avenue.
The second construction season (2023) included work throughout the limits of the initial contract referenced above. Crews completed the installation of the remaining underground utilities and stormwater infrastructure, reconstructed the roadways between Home Avenue and Sears Lane, and constructed the Champlain Parkway between Home Avenue and Lakeside Avenue. Crews began utility and roadway reconstruction work along Lakeside Avenue in June and began roadway rehabilitation and drainage work along Pine Street in August. Throughout the winter crews continued installing traffic signal equipment at the intersections of the Champlain Parkway at Home Avenue, Flynn Avenue, Sears Lane, and Lakeside Avenue.
Project Forecast: Construction activities for the third and final construction season (2024) of the initial contract are anticipated to begin on April 15. Construction activities will take place throughout the initial contract limits and focus on completing all remaining work included in the initial contract.
Between Home Avenue and Lakeside Avenue, work will include final line striping, completion of the traffic signals, landscaping and tree planting, the installation of permanent roadway signage, and general clean-up.
Along Lakeside Avenue, crews will pave the final lift of pavement on the roadway and driveways, install final line striping, construct the shared-use path, landscape and general clean up.
The bulk of the work this construction season will take place along Pine Street between Lakeside Avenue and Kilburn Street. Crews will install the remaining sections of curb, construct the remaining portions of the eastside sidewalk, complete sewer manhole adjustments and drainage structure rehabilitation, pave the final lift of pavement on the street and shared-use path, install final line striping and permanent roadway signage, install the raised intersections at Kilburn Street, Marble Avenue, and Howard Street, construct the bus shelters, and complete landscaping and general clean up.
In addition, crews will construct the shared-use path connection between the south end of Pine Street and Shelburne Street (Route 7) that will run along Potash Brook.
Construction on the initial contract of the Champlain Parkway project is anticipated to be completed this summer.
|