Beginning December 5, a year-long Florida Department of Transportation improvement project along U.S. 1 will begin. Among the improvements will be:
-
Upgrading traffic lights at Sunset Drive, SW 70 Street, Alhambra Circle, and Stanford Drive.
- Constructing traffic islands at the intersections of SW 62 Avenue, SW 71 Street, and Santona Street.
- Extending the left turn from northbound SR 5/US 1 to westbound Sunset Drive.
- Upgrading vehicular and pedestrian signals, signage and pavement markings.
- Reconstructing pedestrian sidewalks, curb ramps, and curb and gutters.
- Replacing existing guardrail.
- Rehabilitating the bridge over the Coral Gables Waterway.
To reduce the impact on travelers, lane closures will only be during less congested, off-peak hours. These include non-rush hours:
- 9:00am - 3:30pm, weekdays
- 10:00pm - 6:00am, Sunday through Thursday nights
- 11:00pm - 7:00am, Friday and Saturday nights
If there is a need to detour traffic, signs will be posted along U.S. 1.
|