Phase 1 is currently under construction and anticipates substantial completion in fall 2024. Phase 1 includes a 30- acre marshaling space containing a heavy-lift wharf and uplands that will facilitate the offloading, testing, inspection, and pre-assembling of wind turbine generation components before their installation offshore. This process is commonly referred to as OSW Marshaling.
The wharf is 1,080 linear feet and comprises delivery and installation berths to support load-in and load-out operations. Further, the pile-supported pier has a load-bearing capacity of 6,200 pounds per square foot at the concrete deck surface.
The port has also been future-proofed with the inclusion of a breasting dolphin and two mooring dolphins to accommodate a US flagged wind turbine installation vessel.
To date, all dredging associated with Phase 1 has been completed in coordination with NJEDA partners, the NJDOT Office of Maritime Resources and AECOM-Tishman. The access channel and berth areas are dredged to -35.5 feet, with an installation berth pocket of -47.5 feet.
Parcel B1 commenced construction for Stage 1 earthwork operations January 2024 and has completed initial filling operations, wick drain installation, and geotechnical monitoring instrumentation installation.
Surcharge embankment construction, MSE wall construction, and geotechnical instrumentation monitoring is actively on-going and progressing well.
The Parcel B1 earthwork project is approximately 50% complete. A test pile program consisting of 44 precast concrete piles was completed in April 2024 to inform the wharf design for B1.
Parcel C1 surcharge embankment was fully removed in early May 2024 and the area prepared for future sitework construction operations.
|