CONSTRUCTION PHASING: The majority of construction activities for this project will be performed Sunday through Thursday, during the nighttime hours of 7 p.m. and 7 a.m. This spring, crews will work on U.S. 4 and U.S. 7, milling and paving the leveling course of asphalt.
In early summer, crews will adjust structures, make improvements to sidewalks, install traffic signs, and upgrade the traffic signals on U.S. 4 and U.S. 7. Crews are also scheduled to mill and pave the leveling course of asphalt on U.S. Business Route 4 (U.S. BUS 4).
In late summer, crews will reconstruct the railroad crossing on U.S. 7, begin paving the wearing course of asphalt on U.S. 4 and U.S. 7, and make improvements to sidewalks, adjustments to structures, upgrades to traffic signals, and install traffic signs on U.S. BUS 4. The reconstruction of the railroad crossing will require a temporary closure of U.S. 7 near the intersection of Park Street.
In the fall, crews are anticipated to finish paving on U.S. 4, U.S. 7, and U.S. BUS 4, and install pavement markings throughout the project area, including the new roadway configuration with supporting signs. Crews will also conduct clean-up and inspection work project-wide.
Any project activities remaining in late fall/early winter will be completed the following Spring of 2025. The project is scheduled for completion by the Summer of 2025.
LOCATION: The project area encompasses U.S. Route 7 from near Cold River Road and extending north to Lincoln Ave, U.S. Business Route 4 from near Ripley Road and extending east to the intersection with U.S. 7, and U.S. Route 4 (Woodstock Ave) from the intersection with U.S. 7 and extending east to Gleason Road.
|