Good Morning,
River Road is coming along well, curb and gutter is getting installed near ABS Global and asphalt paving from ABS to the southern bridge will occur late next week after Windsor Road is paved. Work continues on storm sewer installation north of Woods Glen Court to South Street. We ask everyone that lives on Daley Road and Woods Glen Court to continue coming from the north (South Street) until further notice. NO traffic will be able to go south from Woods Glen Court, the contractor is excavating the base and installing the new road base. People going to ABS Global and Little University please continue coming from the south (Innovation Drive) until further notice. Thank you for your patience.
Greg
Greg Hall
Public Services Operations Supervisor
Village of DeForest
608-807-7023