Good morning,

River Road reconstruction is off to a good start, storm sewer is going in and will be completed south of the Woods Glen bridge. The contractor will be working north from the bridge to South Street the next couple weeks. Expect short delays near Woods Glen for utility installation at the intersection. The contractor will move out of the way as cars enter and exit. There is roughly 2-3 days worth of work at this intersection. 

The contractor is also starting to undercut and grade for the base south of the Little University of Vienna. The contractor will try to keep traffic coming in from both directions on River Road. If you have any questions or concerns, please call me at 608-807-7023 or email.

Greg