This is an update on activities related to the Eversource 115-kilovolt (kV) Underground Transmission Project in Sudbury and Hudson. Across the inactive MBTA rail corridor, crews are accessing manhole locations to prepare the underground duct bank system for cable installation by proofing the underground conduit. Crews have also resumed work in the Hudson streets.


Work Hours

  • Sudbury - Approved work hours are 7 a.m. to 6 p.m., Monday to Friday. During the cable installation process, crews will work from 7 a.m. to 5 p.m., Monday to Saturday All other activities in the corridor will happen from 7 a.m. to 4 p.m. 
  • Hudson - Approved work hours are 7 a.m. to 6 p.m., Monday to Friday. Crews will be working in the Hudson roads, from 7a.m. to 5 p.m., Monday to Friday. During cable installation, crews will be active from 7 a.m. to 5 p.m., Monday to Saturday. 


Occasional activities may extend beyond the approved hours, due to unforeseen circumstances, based on approval from local officials. Crews work between manholes (MHs) placed along the project route. For a closer look, view the project map.



Hudson Activities

  • Road work in the Hudson streets, on Forest Avenue, has resumed between MH2 and MH1. Crews are working west of Marlboro Street on Forest Avenue moving toward Hudson Light and Power excavating and installing duct bank. One lane of alternating traffic will be maintained whenever possible.  
  • On Wilkins Street, north of Orchard Drive, one crew is excavating, removing ledge, and installing duct bank to tie into the inactive MBTA rail corridor.  
  • Starting as soon as April 16, a third crew will begin relocating a distribution duct bank underground outside of Hudson Light & Power on Forest Avenue to make room for the new underground transmission duct bank. 
  • At Bridge 130, between Chestnut St and Main St, crews are installing transitions pours.  
  • From Parmenter Road to the Town Line, crews will be working on cable installation. 
  • Saturday, April 6th, crews may be working on cable installation between Parmenter Road and White Pond Road. 

 


Sudbury Activities

  • Crews are accessing manhole locations underground in Sudbury throughout the MBTA corridor to proof the recently installed transmission conduit. This process takes several hours and is in advance of the cable installation.  


*Due to the complexities of underground construction and weather, the two-week schedule described above is subject to change.

Stay Informed

Eversource is committed to being a good neighbor and doing any work with respect for you and your property. If you have questions, please contact us directly or click on one of the resources below.


Si necesita que le traduzcan esta notificacio ́n, envi ́enos un correo electro ́nico a Projectinfoma@eversource.com y escribe “S-H” en el asunto.
如果您需要本通知的翻譯版本,請寄送電郵至Projectinfoma@eversource.com,並在主題欄中輸入 “S-H
如果您需要本通知的翻译版本,请发电子邮件到 Projectinfoma@eversource.com,并在主题栏中输入 “S-H
Facebook  Twitter  Instagram  Youtube  Linkedin  
Address: 247 Station Drive
Westwood, MA 02090
Phone: 1-833-836-0302
Email Us