Mount Vernon Rd from 14th to 20th

Construction Update | 10-12-23


With the center lanes closed this past week and traffic running in the outside lanes, progress is being made on the center medians. The curb, gutter, and colored concrete are complete and the decorative concrete pavers are scheduled to be installed this week.

 

At the end of this week or early next week, the south lanes will be closed and traffic will be switched to run head-to-head in the north lanes. This will allow for the placement of the final asphalt in the south lanes, along with the permanent pavement markings. This traffic pattern is expected to be in effect for approximately one week.

 

When work is complete in the south lanes, the outside lanes will be closed and traffic will run in the inside lanes. This will be the final phase of work for this construction season and will allow for the completion of the concrete pavers adjacent to the sidewalk, grading, sodding, installation of streetlights, and installation of traffic signals.

 

Thank you for your continued patience as we are wrapping up this project for the year.

CONTRACTOR

Pirc Tobin

Craig Tobin

319-842-2130

CITY PROJECT MANAGER

Jennifer Selby

319-286-5622

j.selby@cedar-rapids.org


CITY CONSTRUCTION MANAGER

Joel Robinson

319-286-5533

j.robinson@cedar-rapids.org

Visit Our Project Webpage

About the project:

The Mount Vernon Road project stretches from 14th Street to 20th Street and includes: pavement widening; raised medians with aesthetic improvements; new sidewalk and existing sidewalk repairs; an asphalt overlay; utility improvements; traffic signal upgrades; and traffic safety improvements to the intersections at 15th and 19th Streets. This is a two-season construction project with work from 14th Street to 17th Street occurring in 2023 and from 17th Street to 20th Street in 2024.