In October, crews continued construction activities along the corridor:
Area 1 West: Reston Avenue to Baron Cameron Avenue:
- Completed the extension of the Dog Run box culvert on the north side of Route 7 between Northfalls Court and Utterback Store Road.
- Continued drilling noise barrier foundations and earth-moving activities between Reston Avenue and Utterback Store Road.
- Began construction of noise barriers.
- Performed storm sewer installation between Reston Avenue and Reston Parkway, and completed storm sewer installation between Reston Parkway and Utterback Store Road.
- Performed cement stabilization of the subgrade and placed cement-treated aggregate for future westbound Route 7 lanes between Great Passage Boulevard and Amanda Drive.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
- Completed construction of the common duct bank between Delta Glen Court and Carpers Farm Way.
- Continued earth-moving operations between Baron Cameron Avenue and Carpers Farm Way.
- Completed storm sewer installation and performed fine grading and cement stabilization of the subgrade along eastbound Route 7 between Baron Cameron Avenue and Colvin Forest Drive.
- Stage 2 construction pending right-of-way acquisition.
- Continued relocation of communication utilities.
- Continued the realignment of Colvin Run.
- Installed sheet pile in the Colvin Run area east of Carpers Farm Way.
- Completed installation of the west half of the box culvert under Carper's Farm Way.
- Continued storm sewer and completed water line installation for Route 7 westbound lanes between Faulkner Drive and Trotting Horse Lane.
- Began fine grading and cement stabilization of the subgrade for Route 7 westbound lanes between Faulkner Drive and Trotting Horse Lane.
- Completed storm sewer and water line installation for Route 7 westbound lanes between Lewinsville Road and Jarrett Valley Drive.
- Continued construction of stormwater management pond near Trotting Horse Lane.
- Continued earth-moving operations and completed fine grading for Route 7 westbound lanes between Lewinsville Road and Jarrett Valley Drive.
Design work continues for lighting and landscaping. Third-party utility design and relocation activities are also ongoing.