An update from the City of Mill Valley and the Mill Valley Chamber of Commerce on construction dates, times, parking, and more!
Miller Avenue Construction Update - Week of July 11 - 15, 2016

The Miller Avenue Streetscape Project is an 18-month construction project to repair infrastructure and improve multi-modal use of Miller Avenue, including addressing safety for pedestrians and bicyclists of all ages and abilities, providing better transit access, and improving motorist safety.

Construction began the week of June 13, 2016 and will continue through Fall 2017. Please note that all construction schedules are subject to change due to weather restrictions and other unforeseen delays.

Here is the latest news on the Miller Avenue Streetscape Project:

What Happened Last Week:
The contractor installed temporary parking striping in the areas where asphalt was placed after the removal of center medians between Willow Street and Valley Circle. Work crews installed underground water services between La Goma Street and Valley Circle, and installed underground storm drain lines between Willow Street and Locust Avenue. Work crews removed concrete curb, gutter and sidewalk along the north side of Miller Avenue between Willow Street and Locust Avenue.

What is Happening This Week: 
The contractor will install the main line underground storm drain lines between La Goma Street and Valley Circle, as well laterals off the main line. Work crews will remove concrete curb, gutter and sidewalk along the north side of Miller Avenue between 319 Miller Avenue and Locust Avenue. Once the concrete is removed, underground electrical and irrigation service lines for future street lighting and landscaping will be installed. The new concrete curb, gutter and sidewalk will be replaced over the next three weeks.

Concurrent with the Miller Avenue Streetscape Project is a PG&E Gas Main and Service Lateral Replacement Project. PG&E will begin work this this Thursday at Gomez Way and work their way towards Reed Street. Please anticipate lane shifts and some parking impacts during this project. Work on this project will take place weekdays from 8 am to 5 pm.

What to Expect in Upcoming Weeks:
The contractor will continue removing curb, gutter and sidewalk, along the north side of Miller Avenue between 319 Miller Avenue and Locust Avenue, as well as Valley Circle to Evergreen Avenue. Work crews will install new electrical and irrigation services after the concrete is removed in preparation for the placement of new concrete curb, gutter and sidewalk. Installation of new underground domestic and fire water services, and storm drains lines will continue. Work crews will install new concrete curb, gutter and sidewalk between 319 Miller Avenue and Locust Avenue.

The current phase of the PG&E Gas Main and Service Lateral Replacement Project is anticipated to continue until mid-September.
Frequently Asked Questions
We recently received a number of questions and comments about the project and wanted to provide additional information - such as:
  • Why were the trees on Miller Avenue cut down? Will the City plant new trees?
  • Is Miller Avenue being reduced to one lane? 
  • Will there be any additional safety precautions added to the crosswalk at Evergreen and Miller? (In front of Whole Foods?) 
And More..
Where Can I Park?

Click here for a map of alternative parking spaces during the Miller Avenue Streetscape Project. Please note that construction may affect the availability of some spaces on any given day. 
Support Local Miller Ave Businesses - MillerUP!


Follow the latest news and promotions for the Miller Avenue Business District using the hashtag #millerup

During the project, Miller Avenue-area businesses need your help! Please support them.

Check out the MillerUp info from Enjoy Mill Valley here.

Learn More about the MillerUP Business Support Program here.
Thank You for your Patience During Construction

The City recommends that motorists: 
  • Add time to your trip and plan ahead.
  • Drive slowly through the construction zone. 
  • Please be courteous to your neighbors and do not to cut through the residential side streets during the construction period. 
City and Construction Management staff are making every effort to mitigate impacts during construction and are working with the Mill Valley Chamber of Commerce to notify local businesses and residents of the planned work. City and Construction Management staff will provide regular updates to the community regarding the project.
Questions?

Construction Specific Questions:  
Please contact 4LEAF Construction Management 
Phone: (415) 328-6972 
Email:  mthrailkill@4leafinc.com 

General Questions:
Please contact Becky Murray, Administrative Assistant 
City of Mill Valley 
Phone: 415-384-4835 


More info: 

Download the Primer on the Miller Avenue Streetscape Project: Click here for a more in-depth look at the Miller Avenue Streetscape Project: timeline, budget, map, and a history of community involvement. 

Miller Avenue Area Businesses: Do we have your contact info? If you are not sure, please contact Becky Murray, Administrative Assistant: bmurray@cityofmillvalley.org or call 415-384-4835. Please let us know your name, business name and address, email address and phone number. 

Miller Avenue History of Community Involvement: Click here to learn about the history of community involvement and the input and guidance by community members through the work of the City Council, Planning Commission and various committees over the years. 

Stay Informed
                      City of                                                 Mill Valley
                      Mill Valley                                            Chamber of Commerce  
                       www.cityofmillvalley.org                         www.millvalley.org