In April, crews continued construction activities along the corridor, including:
- Difficult Run/Colvin Run area
- Utility installation work
- Paving and striping for the lane shift between Carpers Farm Way/Colvin Run Road and Serenity Woods Lane/Faulkner Drive
- Storm sewer installation between Reston Avenue and Reston Parkway, and between Utterback Store Road and Carpers Farm Way
- Clearing and grading for a stormwater management pond west of Baron Cameron Avenue
- Relocation of communication lines between Reston Parkway and Utterback Store Road
- Earth-moving operations between Reston Avenue and Riva Ridge Drive
- Fine grading for permanent pavement between Reston Parkway and Utterback Store Road
- Cement stabilization, concrete-treated aggregate, and underdrain installation between Baron Cameron Avenue and Carpers Farm Way
- Grading and stone placement for temporary pavement in the median between Faulkner Drive and Towlston Road
- Shoulder strengthening and asphalt placement between Faulkner Drive and Towlston Road.
Design work continues for lighting and landscaping and the electrical and intelligent transportation systems (ITS). Third-party utility design is also ongoing.
Click here to learn more
on the design and construction schedule, environmental efforts, right of way, noise walls and other project details.