In April, crews continued construction activities along the corridor:
Area 1 West: Reston Avenue to Baron Cameron Avenue:
- Completed noise barrier panel installation between Reston Avenue and Utterback Store Road.
- Installed permanent signal poles at Reston Parkway and Utterback Store Road.
- Completed construction of the curb along westbound Route 7 between Reston Parkway and Utterback Store Road.
- Storm sewer installation and earth-moving activities continued between Reston Avenue and Baron Cameron Avenue.
- Placed cement-treated aggregate and base asphalt between Amanda Drive and Baron Cameron Avenue.
Area 1 East: Baron Cameron Avenue to Colvin Forest Drive:
-
Completed testing of the relocated segment of the Fairfax County Water Authority's 54" water main on the east side of Colvin Forest Drive along eastbound Route 7.
- Stage 2 construction pending right-of-way acquisition.
- Activated the new Colvin Run stream channel.
- Began excavation for the retaining wall between eastbound Route 7 and the Colvin Run stream channel.
- Completed the installation of the concrete footings, arch sections and wingwalls for the south half of the pedestrian tunnel.
- Placed cement-treated aggregate and base asphalt, followed by underdrain installation and curb stone placement along westbound Route 7 between Middleton Ridge Road and Trotting Horse Lane.
- Began grading along westbound Route 7 between Trotting Horse Lane and Forestville Drive.
- Completed the water main relocation between Beulah Road and Towlston Road.
- Placed cement-treated aggregate and base asphalt along eastbound Route 7 between Old Ash Grove and Jarrett Valley Drive.
Third-party utility design and relocation activities are also ongoing.