In February, crews continued construction activities along the corridor, including:
- Difficult Run/Colvin Run area--clearing, erosion & sediment (E&S) controls, utility installation and bridge median removal
- Clearing and E&S controls along eastbound Route 7 from Baron Cameron Avenue to Carpers Farm Way
- Topsoil stripping between Reston Parkway and Utterback Store Road
- Earth-moving operations between Reston Avenue and Bishopsgate Way
- Storm sewer installation between Reston Avenue and Delta Glen Drive
- Relocation of water main between Reston Avenue and Reston Parkway
- Placing barrier along the median of Route 7 between Lewinsville Road and Jarrett Valley Drive.
Design work continues for lighting and landscaping and the electrical and intelligent transportation systems (ITS). Third-party utility design is also ongoing.
Tabulation of Potential Noise Barrier Public Input Survey Questionnaires from
benefited
parcel owners and tenants along the corridor continued through February.
Click here to learn more
about the noise wall process.