In February, crews continued construction activities along the corridor:
Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
- Continued construction of the shared-use paths along Route 7.
Area 2: Baron Cameron Intersection
- Constructed the curb for the eastbound Route 7 turn lane to Baron Cameron Avenue.
- Continued construction of the improvements on Baron Cameron Avenue between Route 7 and Hunter Gate Way.
Area 3: Difficult Run Area (Colvin Forest Drive to Faulkner Drive)
- Completed construction of the backwalls of the bridge abutments.
- Began forming the bridge deck and installing the deck rebar for the new Difficult Run bridge on westbound Route 7.
- Continued storm sewer installation between the east end of Colvin Run Road and Difficult Run, and between Difficult Run and Faulkner Drive.
Area 4: Faulkner Drive to Jarrett Valley Drive
- Continued noise barrier foundation drilling along eastbound Route 7 between Trap Road and Jill's House.
- Continued noise barrier post installation between Andrew Chapel Cemetery and Jill's House.
- Continued construction of the retaining walls and noise barrier along westbound Route 7 between Forestville Drive and Trotting Horse Lane.
- Completed construction of the retaining wall along eastbound Route 7 near Serenity Woods Lane.
- Continued excavation for the stormwater management pond on the west side of McLean Bible Church.
- Grading, placement of cement-treated aggregate, and base asphalt paving was completed along eastbound Route 7 between Serenity Woods Lane and Atwood Road.
|