What's the latest on the referendum work?
Business Administrator Tom Eldridge has provided an update on projects included in the referendum passed by Lawrence voters in January 2018. See details below.
School abbreviations are: Slackwood (SWS), Eldridge Park (EP), Intermediate School (LIS), Middle School (LMS), High School (LHS), Lawrenceville (LES), Ben Franklin (BF).
The Security Vestibule Projects (SWS, EP, LIS, LMS) have been awarded and work will be complete by this summer, if not sooner.
The
Modular Building Window projects (SWS, EP, LES, BF) have been awarded and work will be complete by this summer. Installation is expected to occur during this winter/spring.
The
Modular Building Ramp/Stairs projects (SWS, EP, LES, BF) have been awarded and work will be completed this summer.
The
Modular Building Siding projects (SWS, EP, LES, BF) have been rejected and we will rebid next month and awarding this winter. Work will be completed this summer.
The HVAC Projects (air conditioning) are scheduled to be awarded next month: PLEASE NOTE COMPLETION DATES
BF: 100% complete this summer. No electrical upgrades necessary (completed with additions in 2005)
LES: 100% complete this summer. No electrical upgrades necessary (completed with additions in 2005)
SWS: Electrical upgrades this summer to accommodate new units. AC units installed summer 2020.
EP: Electrical upgrades this summer to accommodate new units. AC units installed summer 2020.
LIS: Electrical upgrades this summer to accommodate new units. AC units installed summer 2020.
LMS: Electrical upgrades this summer to accommodate new units. New Boiler Piping run throughout building this summer. AC units installed summer 2020. New Boiler (switch from steam to hot water) Summer 2020.
LHS: 100% complete this summer. No electrical upgrades necessary (completed with additions in 2005). New Boiler installed this summer.
The Telephone Systems/Security Projects: District-wide, currently under development (Deciding on systems)
The Elevator Project: LMS only. Design Development (Completion: summer 2020)