I-495 (CAPITAL BELTWAY)
Tuesday, September 3, through Thursday, September 5, 9:30 a.m. to 2:30 p.m.
Single left and/or right lane closure on southbound I-495 between George Washington Memorial Parkway and Lewinsville Road for road widening work.
Tuesday, September 3, through Thursday, September 5, 10 a.m. to 3 p.m.
Single left and/or right lane closure on northbound I-495 between Lewinsville Road and George Washington Memorial Parkway for road widening work.
Tuesday, September 3, through Thursday, September 5, 9:30 p.m. to 5 a.m. and Friday, September 6, 10 p.m. to 7 a.m.
Triple lane closures with periodic total traffic stoppages on north- and southbound I-495 between George Washington Memorial Parkway and Dulles Toll Road for demolition of the old Live Oak Drive Bridge, overhead sign work, and girder setting at the new Old Dominion Drive Bridge. One lane will remain open, with full traffic stoppages of up to 30 minutes each occurring between midnight and 5 a.m.
Click here for more information about the demolition of the old Live Oak Drive Bridge.
Click here for more information about the overhead sign work and girder setting at the new Old Dominion Drive Bridge.
Friday, September 6, 9:30 a.m. to 12 p.m.
Single lane closure on north- and/or southbound I-495 throughout the project corridor as needed for maintenance work and traffic management.
George Washington Memorial Parkway to I-495 South
Tuesday, September 3, through Friday, September 6, 10 p.m. to 5 a.m.
The on-ramp from north/westbound George Washington Memorial Parkway to southbound I-495 will be closed for bridge demo work. A signed detour will be in place directing motorists across the American Legion Bridge into Maryland, to Clara Barton Parkway (Exit 41), and then back toward Virginia.
Click here for more information about the demolition of the old Live Oak Drive Bridge.
I-495 South Collector Road
Tuesday, September 3, through Friday, September 6, 10 p.m. to 5 a.m.
The collector road from southbound I-495 to the exit for Georgetown Pike (Exit 44) will be closed for bridge demo work. A signed detour will be in place directing motorists to Exit 46 B to access Route 123 North to then take the exit for I-495 North back toward Georgetown Pike.
Click here for more information about the demolition of the old Live Oak Drive Bridge.
|