495 NEXT LANE CLOSURES & TRAFFIC CHANGES

June 7 - June 17, 2024

The following construction-related lane closures and traffic changes are planned in the I-495 Express Lanes Northern Extension (495 NEXT) project corridor. Travelers may encounter delays in this area. All work is subject to change based on weather and other factors.


Visit 511virginia.org for real-time information on work zones and lane closures.

495 NEXT Project Area Map

495 NEXT Project Area Map

What's Happening This Weekend

  • I-495 North – Nighttime double lane closure from 10 p.m. to 7 a.m. beginning tonight, Friday, June 7, for a traffic shift operation at the Dulles Corridor interchange. Learn more about the work here.

Highlights for Next Week

  • I-495 North and South – Day and nighttime single and multi-lane closures


  • I-495 South – Double right lane closure from 2 a.m. to 5 a.m. on Monday, June 10, at the Georgetown Pike interchange for a bridge deck pouring operation. The on-ramp from the collector-distributor road to southbound I-495 also will be closed for this work. Learn more about the work and detour here.


  • Live Oak Drive & Balls Hill Road – Daytime flagging operations


  • Georgetown Pike – Daytime single and nighttime single and multi-lane closures


  • Dulles Toll Road – Daytime single and nighttime double lane closures


  • Dulles Toll Road East Ramp to I-495 North – The ramp from eastbound Dulles Toll Road/Airport Access Road (Route 267) to northbound I-495 will be closed nightly with a detour for bridge demolition work. Learn more about the work and detour here.

Lane Closures 

I-495 (CAPITAL BELTWAY)


Friday, June 7, 10 p.m. to 7 a.m.

Double lane closure on northbound I-495 between just south of Exit 46B and just south of Lewinsville road for crews to shift traffic onto a new I-495 North bridge over eastbound Dulles Toll Road/Airport Access Road (Route 267) ramp. Learn more about the work here.


Monday, June 10, 2 a.m. to 5 a.m.

Double right lane closure on southbound I-495 at the Georgetown Pike interchange for a bridge deck pouring operation. The on-ramp from the collector-distributor road to southbound I-495 also will be closed for this work. Drivers traveling on the collector-distributor road to access I-495 South will be detoured to the exit for Georgetown Pike (Exit 44) and will continue to the on-ramp from Georgetown Pike to I-495 South. Learn more about the work and detour here.


Monday, June 10, through Thursday, June 13, 10 a.m. to 3 p.m. and Friday, June 14, 10 a.m. to 12 p.m.

Single right lane closure on northbound I-495 between Lewinsville Road and George Washington Memorial Parkway for excavation, embankment, wall, drainage, and bridge work. As needed, this closure may change to an alternating single mobile lane closure for maintenance work and traffic management throughout the project corridor.


Monday, June 10, through Thursday, June 13, 9:30 a.m. to 2:30 p.m.

Single right lane closure on southbound I-495 between Live Oak Drive and Dulles Toll Road for excavation, embankment, wall, drainage, and bridge work. As needed, this closure may change to an alternating single mobile lane closure for maintenance work and traffic management throughout the project corridor.


Monday, June 10, through Thursday, June 13, 9:30 p.m. to 5 a.m. and Friday, June 14, 10 a.m. to 12 p.m.

Alternating single mobile lane closure on north- and southbound I-495 throughout the project corridor as needed for maintenance work and traffic management.


Monday, June 10, through Thursday, June 13, 9:30 p.m. to 5 a.m., Friday, June 14, 10 p.m. to 8 a.m., and Saturday, June 15, 10 p.m. to 9 a.m.

Single left lane closure on northbound I-495 between Exit 45 and Lewinsville Road for bridge demolition work at the Dulles Corridor interchange.

LIVE OAK DRIVE


Monday, June 10, through Friday, June 14, 9 a.m. to 3:30 p.m.

Live Oak Drive will be reduced to a single lane between the Langley Swim and Tennis Club and Green Oak Drive for asphalt demolition. Flagging operations alternating single traffic lanes will be in effect.

BALLS HILL ROAD


Monday, June 10, through Friday, June 14, 9 a.m. to 3:30 p.m.

Balls Hill Road will be reduced to a single lane between Benjamin Street and Live Oak Drive for sound wall and retaining wall excavation work. Flagging operations alternating single traffic lanes will be in effect.

GEORGETOWN PIKE INTERCHANGE


Monday, June 10, through Friday, June 14, 9:30 a.m. to 3 p.m. and 10 p.m. to 5 a.m., Friday, June 14, 10 p.m. to 9 a.m., and Saturday, June 15, 10 p.m. to 8 a.m.

Single lane closure on east- and westbound Georgetown Pike between Balls Hill Road and the I-495 interchange for hauling and drainage work.


Monday, June 10, through Thursday, June 13, 10 a.m. to 3 p.m.

Right shoulder closure with encroachment into the right lane on the exit ramp from northbound I-495 to Georgetown Pike for directional boring work.


Sunday, June 16, from 9 p.m. to Monday, June 17, at 5 a.m.

Double right lane closure on westbound Georgetown Pike at the bridge over I-495 to accommodate a bridge deck pouring operation. The remaining lanes on the bridge will be shifted to accommodate turn and thru lanes in both directions, and stoplights will be adjusted. Learn more about the work here.

DULLES CORRIDOR INTERCHANGE 


Dulles Toll Road


Monday, June 10, through Friday, June 14, 10 a.m. to 3:30 p.m.

Single right lane closure on eastbound Dulles Toll Road (Route 267) from Spring Hill Road to the I-495 interchange for trenching and guardrail work.


Monday, June 10, through Thursday, June 13, 9:30 a.m. to 3 p.m.

Single left lane closure on westbound Dulles Toll Road (267 Connector) from Rt. 123 to the I-495 interchange for roadway work.


Monday, June 10, through Friday, June 14, 10 p.m. to 5 a.m.

Double lane closure on eastbound Dulles Toll Road (Route 267) between International Drive and the I-495 interchange for temporary barrier work.


Monday, June 10, through Thursday, June 13, 8 p.m. to 4 a.m., Friday, June 14, and Saturday, June 15, 8 p.m. to 6 a.m.

The ramp from eastbound Dulles Toll Road/Airport Access Road (Route 267) to northbound I-495 will be closed for bridge demolition work. Motorists will be detoured onto I-495 South using Exit 18A, then will take Exit 46B and continue in the ramp lane to immediately exit onto I-495 North. Learn more about the work and detour here.

Traffic Changes

New Exit Ramp for I-495 North Exit to Dulles Toll Road


Reminder: Motorists traveling on northbound I-495 heading for westbound Dulles Toll Road must take a new, earlier exit. The new exit ramp is located about one-third of a mile ahead of the old, closed Exit 45. To facilitate this new traffic pattern, I-495 has been reduced from four to three lanes for approximately one-half mile near the Dulles Corridor interchange.

George Washington Memorial Parkway West at I-495


Reminder: The ramp from westbound George Washington Memorial Parkway to southbound I-495 (Capital Beltway) was reduced from two lanes to one lane to make room for a construction vehicle haul route that will be separated from traffic by a physical barrier. This traffic change will be in effect throughout construction on the 495 NEXT project.

Project Background

The I-495 Express Lanes Northern Extension (495 NEXT) project will extend the existing 495 Express Lanes north by two-and-a-half miles from the Dulles Corridor interchange to the George Washington Memorial Parkway interchange in the vicinity of the American Legion Bridge. The project will provide new and improved connections at the Dulles Corridor and George Washington Memorial Parkway.


Other project benefits include four miles of new bicycle and pedestrian connections including a shared-use path parallel to I-495 from Lewinsville Road to near Live Oak Drive, replacement or rehabilitation of seven bridges with pedestrian accommodations, replacement of nine existing noise walls and construction of a new noise wall, environmental improvements introducing stormwater management facilities and funding of restoration at Scott's Run stream, and dedicated funding to support transit improvements in the corridor including new bus service over the American Legion Bridge. 

 

495 NEXT is a public-private partnership project between the Commonwealth of Virginia and Transurban, operator of the existing 495 Express Lanes. Lane Construction is the design-build contractor for the project. The new extended lanes are scheduled to open in 2025. 

Learn More About the Project


Check out 495next.vdot.virginia.gov for additional information.


Sign up to receive project email updates.



Laptop showing 495 NEXT website

Questions?

Email: 495NorthernExtension@vdot.virginia.gov

Call: Construction Inquiry Line, 703-592-6430

Virginia Department of Transportation, Michelle Holland, 703-586-0487

Transurban, Amanda Allen, 571-249-8784

Lane Construction, John Undeland, 703-785-3461