Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
- Continued drilling noise barrier foundations along eastbound Route 7 between Bishopsgate Way and Markell Court.
- Started final surface paving and pavement markings on westbound Route 7 between Colvin Forest Drive and Amanda Drive.
Area 2: Baron Cameron Avenue Intersection
-
Completed milling and temporary asphalt removal for Stage 3B.
- Shifted traffic on westbound Route 7 at the Baron Cameron Avenue intersection to the south.
Area 3: Difficult Run Area (Colvin Forest Drive to Faulkner Drive
-
Completed asphalt milling for Stage 3B and placed curb stone between the pedestrian underpass and Faulkner Drive.
- Completed construction of the concrete barrier between the eastbound Route 7 travel lanes and the shared use path on the Difficult Run bridge.
Area 4: Faulkner Drive to Jarrett Valley Drive
- Completed noise barrier panel installation along westbound Route 7 between Towlston Road and 400 feet west of Lyons Street.
- Placed curb, stone, and base asphalt between Faulkner Drive and Beulah Road.
-
Placed stone, installed drop inlet tops for new stormwater management infrastructure, poured curb, and put down base asphalt for Stage 3B between Beulah Road and Lewinsville Road.
- Placed and backfilled curb between Lewinsville Road and Jarrett Valley Drive.
Project-Wide
- Third-party utility relocation activities are ongoing.
- Completed installation of Intelligent Transportation Systems (ITS) fiber optic cable for traffic signal communication throughout the project.
- Continued grading, placement of stone and paving for the shared-use path.
Click here to learn more about the construction schedule, environmental efforts, right of way, noise walls and other project details.
|