Is the project still on schedule?
The project has experienced some weather delays and unknown underground conflicts. However, crews adapted to work on installation of the next underground utility to keep project moving forward while working through an underground conflict impacting current utility main installation. This has helped to keep the project on schedule and moving forward.
Can we expect the traffic pattern to stay in place?
There will be changes to the current traffic pattern as installation of the utilities move east. However, drivers can expect only one lane open to through traffic to continue for some time as the installation of underground utilities moves east.
|