June 2024

I-10 Widening and Reconstruction Project

Monthly Public Outreach and Communication Report

State Project H.004100

Project Status

Construction continues to progress along the westbound corridor of the I-10 Widening and Reconstruction Project. Drainage operations continue along I-10 westbound alongside Baywood Ave. from E. Lakeshore to Ebony Ave., with storm drain pipes and catch basins being installed. Additionally in this area, crews continue drilling foundation shafts and pouring concrete for the abutment wall near I-10 westbound near E. Lakeshore Dr. Night work will continue through August between the hours of 3 p.m. and 7 a.m., weather permitting.

 

Permanent pile driving operations remain ongoing in City Park Lake from Monday through Saturday during daytime hours. This work is necessary to construct the bridge piers for the westbound bridge widening, with work anticipated to be completed late summer, weather permitting.

 

While work is ongoing, residents and motorists throughout the corridor can expect to see an increase in truck traffic, as well as an increase in noise during the day. Construction activities continue to be monitored by various noise and vibration monitors throughout the corridor. 

On November 27, 2023, E. Lakeshore Dr. was closed where it passes beneath I-10 as depicted in red on the accompanying diagram. This local street will remain closed for approximately three years while crews work on the permanent widening of I-10 over City Park Lake. Northbound and southbound motorists on E. Lakeshore Dr. are advised to use Dalrymple Dr. for the duration of this closure.  


This portion of E. Lakeshore Dr. will not be accessible to motorists, pedestrians or bicyclists as this is an active construction site.

Pile driving operations continue in City Park Lake on the construction of the permanent bridge piers.

Drainage operations along I-10 WB alongside Baywood Ave.

DOTD's 511LA service provides up-to-date lane closure information. Click here to visit 511la.org

About the Project

The I-10 Widening and Reconstruction Project is currently in Stage 1, which includes the first phase of permanent widening of the westbound City Park Lake Bridge, local roadway modifications, the Dalrymple eastbound service road and westbound exit ramp, and roadway improvements between the City Park Lake Bridge and Perkins Road. This stage is anticipated to be completed late 2025, weather permitting.

Visit I10br.com