Construction continues to progress along the westbound corridor of the I-10 Widening and Reconstruction Project. Drainage operations continue along I-10 westbound alongside Baywood Ave. from E. Lakeshore to Ebony Ave., with storm drain pipes and catch basins being installed. Additionally in this area, crews continue drilling foundation shafts and pouring concrete for the abutment wall near I-10 westbound near E. Lakeshore Dr. Night work will continue through August between the hours of 3 p.m. and 7 a.m., weather permitting.
Permanent pile driving operations remain ongoing in City Park Lake from Monday through Saturday during daytime hours. This work is necessary to construct the bridge piers for the westbound bridge widening, with work anticipated to be completed late summer, weather permitting.
While work is ongoing, residents and motorists throughout the corridor can expect to see an increase in truck traffic, as well as an increase in noise during the day. Construction activities continue to be monitored by various noise and vibration monitors throughout the corridor.
|