SHARE:  

PLAN AHEAD

EUCLID AVENUE

EXTENDED STREET AND RAMP CLOSURES

Between Friday, May 17 at 9:00 p.m. and Monday, May 20 at 5:00 a.m. there will be street lane closures, full street closures, and ramp closures for paving on Euclid Avenue:

  • Northbound (NB) Euclid Avenue from 6th Street to 8th Street will be reduced to one lane during daytime hours (5:00 a.m. to 9:00 pm.) and closed during nighttime hours (9:00 p.m. to 5:00 a.m.)
  • Eastbound (EB) I-10 Euclid Avenue on-ramp closed nightly from 9:00 p.m. to 5:00 a.m.
  • Westbound (WB) I-10 Euclid Avenue loop on-ramp will be closed from Friday, May 17 at 9:00 p.m. through Sunday, May 19 at 9:00 a.m.

UPCOMING ACTIVITY

Construction of the I-10 Express Lanes is approaching 95% complete. Crews continue to work throughout the ten-mile corridor on installing barriers, reconstruction of barriers and retaining walls, utility relocation, and pavement rehabilitation. Traffic patterns may change on freeway and local streets as lane configurations are reconstructed.


Dates are subject to change. Detour routes will be posted. Additional information including schedules and locations will be shared and posted to the project Google Map at goSBCTA.com/i10corridor.

Upcoming Extended Street and Ramp Closures for Paving


  • Scheduled for Friday, May 31 at 9:00 p.m. through Monday, June 3 at 5:00 a.m. Southbound (SB) Euclid Avenue between 8th Street and 6th Street will be reduced to one lane during daytime hours and closed during nighttime hours. The WB I-10 Euclid Avenue on-ramp and EB I-10 off-ramp will be closed during nighttime hours. Detour routes will be posted.


Motorists are encouraged to plan ahead, use alternate routes, and follow construction signage.

LEARN MORE ABOUT I-10 EXPRESS LANES CONSTRUCTION IN YOUR CITY

(Click the green boxes below)

MONTCLAIR
ONTARIO
UPLAND

CONSTRUCTION ACTIVITIES -

Week of May 20, 2024

Construction will generally occur Monday through Friday during daytime (7:00 a.m. to 4:00 p.m.) and nighttime (9:00 p.m. to 5:00 a.m.) hours, except as noted. All construction is dynamic and the schedule is subject to change. Please check the Google Map for the most updated closure and detour information.

BRIDGES

Work continues on the remaining bridges that are being replaced, widened, or improved to accommodate the widening of the freeway. Work on the bridges may be loud and you may feel vibration at times during both daytime and nighttime hours.


Anticipated completion in spring 2024:


  • San Antonio Creek Channel: The I-10 over San Antonio Creek is being widened.


  • Monte Vista Avenue: The widening of the I-10 over Monte Vista Avenue is complete. Crews continue to relocate utilities on Monte Vista Avenue under the I-10. The street may be reduced to one lane in each direction during daytime hours and may be closed nightly from 9:00 p.m. to 5:00 a.m., Monday through Saturday. Daytime and nighttime activities include utility work and paving.


  • Euclid Avenue: Scheduled for Friday, May 17 at 9:00 p.m. through Monday, May 20 at 5:00 a.m. NB Euclid Avenue from 6th Street to 8th Street will be reduced to one lane during daytime hours and closed during nighttime hours.


  • Vineyard Avenue: Work continues on the west side of the bridge.


Anticipated completion in summer 2024:


  • 4th Street: Crews continue to relocate underground utilities at 4th Street. 4th Street between El Dorado Avenue and Baker Avenue is reduced to one lane in each direction during daytime hours and may be closed during nighttime hours (businesses will remain accessible). Daytime and nighttime activities include placing the 4th Street EB I-10 off-ramp curb, gutter and sidewalk.


  • 6th Street: Daytime and nighttime activities include installing approach slabs.

Reconstruction is complete on several bridges. At some locations crews continue to work on sidewalks, approach slabs, barriers, paving, and decorative work.

  • I-10 Over San Antonio Wash
  • I-10 over Monte Vista Avenue
  • I-10 over Central Avenue
  • I-10 over Benson Avenue
  • I-10 over Mountain Avenue
  • San Antonio Avenue over I-10
  • Sultana Avenue over I-10


  • Campus Avenue over I-10
  • I-10 over Grove Avenue
  • I-10 over 4th Street
  • I-10 over Holt Boulevard
  • Milliken Avenue over I-10
  • Cucamonga Wash Bridge over I-10
  • I-10 over Day Creek Channel
I-10 FREEWAY LANES AND CONNECTORS

Freeway lane closures are necessary for crews to perform maintenance and rebuild retaining walls, sound walls, and bridges. Detour routes will be posted.


  • Scheduled intermittent nighttime connector ramp closures (11:00 p.m. to 5:00 a.m.) on EB I-10 to NB/SB I-15 and westbound (WB) I-10 to NB/SB I-15.


  • Intermittent nighttime lane closures (9:00 p.m. to 5:00 a.m.): EB and WB I-10 between Fairplex Drive and I-15. At least one lane in each direction on I-10 will remain open.


  • Intermittent daytime lane closures: (9:00 a.m. to 2:00 p.m.): EB and WB I-10 between Fairplex Drive and I-15. Four lanes in each direction on I-10 will remain open.
I-10 ON- AND OFF-RAMPS

Intermittent nighttime EB and WB I-10 on- and off-ramp and ramp lane closures will occur throughout the project corridor. Detour routes are posted.


  • Scheduled intermittent nighttime EB and/or WB on- and off-ramp closures: Indian Hill Boulevard, Monte Vista Avenue, Central Avenue, Holt Boulevard, Vineyard Avenue, Archibald Avenue, Haven Avenue, Milliken Avenue, and Etiwanda Avenue.


  • EB I-10 Euclid Avenue on-ramp will be closed nightly from 9:00 p.m. to 5:00 a.m. beginning Friday, May 17 through Sunday, May 19 (into the following morning)


  • WB I-10 Euclid Avenue loop on-ramp will be closed Friday, May 17 at 9:00 p.m. through Sunday, May 19 at 9:00 a.m.
LOCAL STREETS AND WALLS

Crews are relocating and installing utilities and completing concrete and asphalt work on streets and sidewalks adjacent to the I-10; at times this work may be loud and you may feel vibration. One side of the sidewalk will always remain open. Flaggers may be onsite to direct traffic. Please check the Google Map for the most updated information including closures, detours, and wall locations.


Daytime and/or nighttime lane closures (streets will remain open):

  • Central Avenue, Mountain Avenue, Euclid Avenue, and Grove Avenue


Nighttime street closures; businesses will remain accessible:

  • Monte Vista Avenue: NB/SB street closed under I-10
  • Palo Verde Street: WB street closed from Central Avenue to Monte Vista Avenue
  • 4th Street: NB/SB street intermittently closed under I-10
  • Euclid Avenue: NB Euclid Avenue will be closed nightly Friday, May 17 through Sunday, May 19 from 9:00 p.m. to 5:00 a.m.


Retaining wall and sound wall locations:

  • There is no scheduled wall work at this time

IN THE COMMUNITY

Join the City of Montclair on Monday, May 27 at 6:00 p.m. for a Memorial Day Ceremony including patriotic songs, readings, and refreshments. Click the image below for more information.

ABOUT THE PROJECT
Phase 1 of SB Express Lanes is located in the southwestern portion of San Bernardino County east of Los Angeles County. The project will provide choices on the I-10 freeway between the Los Angeles/San Bernardino County line and I-15. The project includes two express lanes in each direction to offer trip reliability and ease congestion. In addition, lanes to assist drivers getting on and off the freeway (auxiliary lanes) will be constructed in selected locations. West of Haven Avenue, a single new lane will be constructed and combined with the existing HOV lane to provide two express lanes in each direction. The HOV lane will still be available to motorists, but will increase from 2+ to 3+. East of Haven Avenue, two express lanes will be constructed.

Sign up for text messages by texting i10expresslanes to (888) 525-1021 (Reply STOP to cancel, text HELP for help. Normal text and data message rates may apply.)


Si prefiere recibir información de construcción en español, llame al (877) 55 - SBCTA.

When the new SB Express Lanes on I-10 open in 2024, drivers will be able to enter and exit the lanes from multiple points. Toll pricing will be dynamic and will vary based on demand and distance. A FasTrak® account will be required for drivers to receive the lowest toll price on the new lanes. However, drivers without a FasTrak account will be able to utilize the Pay Online feature within five days of their trip. Have more questions on how the new lanes will work? Check out the SB Express Lanes tab on the project website to view the FAQs.





877-55-SBCTA

info@goSBCTA.com

Facebook  X  Instagram  Linkedin