Issue 45 | February 2023

Along about seven miles of Route 7, we're adding a third lane and shared-use paths in each direction, building a pedestrian underpass to access Colvin Run Mill Park, replacing and raising the bridge over Difficult Run, and making many intersection, bicycle and pedestrian improvements. Learn more.

Construction Updates

In January, crews continued construction activities along the corridor:


Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)


  • Continued construction of the shared-use paths along Route 7.


Area 2: Baron Cameron Intersection


  • Continued construction of the permanent right-turn lane from eastbound Route 7 to Baron Cameron Avenue and additional improvements at the southwest corner of the Route 7/Baron Cameron Avenue intersection.


Area 3: Difficult Run Area (Colvin Forest Drive to Faulkner Drive)


  • Set girders and continued construction of the bridge abutments for the new Difficult Run bridge on westbound Route 7.
  • Continued storm sewer installation between the east end of Colvin Run Road and Difficult Run.


Area 4: Faulkner Drive to Jarrett Valley Drive



  • Continued noise barrier foundation drilling along eastbound Route 7 between Towlston Road and Lucky Estates Drive.
  • Continued noise barrier post installation near Atwood Road.
  • Removed existing asphalt along Route 7 between Beulah Road and Atwood Road, and between Lucky Estates Drive and Lewinsville Road.
  • Began excavation for the stormwater management pond on the west side of McLean Bible Church.
  • Earth-moving activities along eastbound Route 7 commenced between Beulah Road and Atwood Road. 
  • Grading, placement of cement-treated aggregate, and base asphalt paving was completed along eastbound Route 7 between Atwood Road and Towlston Road. 
  • Grading and placement of cement-treated aggregate began along eastbound Route 7 between Lucky Estates Drive and Lewinsville Road. 

Third-party utility design and relocation activities are also ongoing.  


Click here to learn more about the design and construction schedule, environmental efforts, right of way, noise walls and other project details.

Click here to see additional January photos.

Girders are set on the new westbound bridge over Difficult Run.

Work Continues Along Route 7

Construction activities will continue along Route 7 through the winter and spring months. Please see the project website for information on upcoming lane shifts and other roadway impacts. 

Thanks for Giving Our Crews S P A C E

As a reminder, please refrain from walking through work areas with equipment, materials and ongoing construction activities, including the newly-paved shared-use paths along Route 7. If you have questions or concerns about the construction, please give our crews the space they need to work, and call or email us instead of approaching the work site.

833-777-7411

Need to Know More?
You can check out photos and project progress on our website at connectroute7.org. Click News & Updates.

Planned lane closures for the following week are posted each Friday.

Sign Up for Traffic Alerts on Virginia 511

Don't forget you can get the latest on work zones, accidents and other incidents by visiting 511virginia.org, using the Virginia 511 app, or by calling 511 from any phone in Virginia. Visit the site or app to create and configure your account for alerts.

You can also check out updates for major incidents @511northernvirginia on Twitter.