In January, crews continued construction activities along the corridor:
Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
- Continued construction of the shared-use paths along Route 7.
Area 2: Baron Cameron Intersection
- Continued construction of the permanent right-turn lane from eastbound Route 7 to Baron Cameron Avenue and additional improvements at the southwest corner of the Route 7/Baron Cameron Avenue intersection.
Area 3: Difficult Run Area (Colvin Forest Drive to Faulkner Drive)
- Set girders and continued construction of the bridge abutments for the new Difficult Run bridge on westbound Route 7.
- Continued storm sewer installation between the east end of Colvin Run Road and Difficult Run.
Area 4: Faulkner Drive to Jarrett Valley Drive
- Continued noise barrier foundation drilling along eastbound Route 7 between Towlston Road and Lucky Estates Drive.
- Continued noise barrier post installation near Atwood Road.
- Removed existing asphalt along Route 7 between Beulah Road and Atwood Road, and between Lucky Estates Drive and Lewinsville Road.
- Began excavation for the stormwater management pond on the west side of McLean Bible Church.
- Earth-moving activities along eastbound Route 7 commenced between Beulah Road and Atwood Road.
- Grading, placement of cement-treated aggregate, and base asphalt paving was completed along eastbound Route 7 between Atwood Road and Towlston Road.
- Grading and placement of cement-treated aggregate began along eastbound Route 7 between Lucky Estates Drive and Lewinsville Road.
|