In November, crews continued construction activities along the corridor:
Area 1 West: Reston Avenue to Baron Cameron Avenue:
- Continued noise barrier post installation and storm sewer work between Reston Avenue and Reston Parkway.
- Earth-moving and grading activities between Reston Avenue and Utterback Store Road continued.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
- Continued earth-moving operations between Baron Cameron Avenue and Carpers Farm Way.
- Finished cement-treated aggregate and base asphalt placement and completed curb and gutter along eastbound Route 7 between Baron Cameron Avenue and Carpers Farm Way.
- Stage 2 construction pending right-of-way acquisition.
- Continued earth-moving activities between Carpers Farm Way and Colvin Forest Drive.
- Started earth-moving activities between Difficult Run and Faulkner Drive.
- Built temporary access road to the sewer pump station near Difficult Run.
- Completed sheet pile installation in the Colvin Run area east of Carpers Farm Way.
- Continued storm sewer installation for Route 7 westbound lanes between Faulkner Drive and Trotting Horse Lane.
- Placed cement-treated aggregate, installed underdrain, placed base asphalt and commenced curb and gutter installation along westbound Route 7 between Faulkner Drive and Trotting Horse Lane.
- Performed cement stabilization of the subgrade, placed cement-treated aggregate, installed underdrain, placed base asphalt and completed curb and gutter installation between Lewinsville Road and Jarrett Valley Drive.
Design work continues for lighting and landscaping. Third-party utility design and relocation activities are also ongoing.
Click here to learn more on the design and construction schedule, environmental efforts, right of way, noise walls and other project details.