Issue 43 | December 2022

Along about seven miles of Route 7, we're adding a third lane and shared-use paths in each direction, building a pedestrian underpass to access Colvin Run Mill Park, replacing and raising the bridge over Difficult Run, and making many intersection, bicycle and pedestrian improvements. Learn more.

Construction Updates

In November, crews continued construction activities along the corridor:


Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)


  • Continued construction of the shared-use paths along Route 7.
  • Shifted traffic on westbound Route 7 to the north between Colvin Run Road and Baron Cameron Avenue.


Area 2: Baron Cameron Intersection


  • Placed cement-treated aggregate, installed underdrain, constructed curb and gutter, and paved along eastbound Route 7 at Baron Cameron Avenue.
  • Shifted the temporary right-turn lane from eastbound Route 7 to Baron Cameron Avenue to the north in preparation for the construction of the permanent right-turn lane.


Area 3: Difficult Run Area (Colvin Forest Drive to Faulkner Drive)


  • Continued construction of the foundations for the new Difficult Run bridge on westbound Route 7.
  • Continued storm sewer installation between the new pedestrian underpass at Colvin Run Mill Park and Difficult Run.


Area 4: Faulkner Drive to Jarrett Valley Drive



  • Continued noise barrier panel installation along eastbound Route 7 on the east and west sides of Old Ash Grove.
  • Completed curb construction along eastbound Route 7 and paved along eastbound Route 7 between Middleton Ridge Road and Beulah Road.
  • Placed cement-treated aggregate, installed underdrain, constructed curb and gutter, and paved along eastbound Route 7 between Beulah Road and Atwood Road.
  • Continued storm sewer installation between Trap Road and Wolftrap Run Road.
  • Placed cement-treated aggregate, installed underdrain, constructed curb and gutter, and paved along eastbound Route 7 between Trap Road and the east side of McLean Bible Church.


Third-party utility design and relocation activities are also ongoing.  


Click here to learn more about the design and construction schedule, environmental efforts, right of way, noise walls and other project details.

Construction of the new westbound Route 7 bridge over Difficult Run is underway.


Click here to see additional November photos.

Sheet piling is installed at the new Difficult Run bridge.

Work Continues Along Route 7

Construction activities will continue along Route 7 through the winter months. Please see the project website for information on upcoming lane shifts and other roadway impacts. 


Click here for the latest updates on the Washington Gas work that is ongoing along Route 7. For more information on the Washington Gas work, please contact Jeff Hicks, jhicks@washgas.com.

Thanks for Giving Our Crews S P A C E

As a reminder, please refrain from walking through work areas with equipment, materials and ongoing construction activities, including the newly-paved shared-use paths along Route 7. If you have questions or concerns about the construction, please give our crews the space they need to work, and call or email us instead of approaching the work site.

833-777-7411

Need to Know More?
You can check out photos and project progress on our website at connectroute7.org. Click News & Updates.

Planned lane closures for the following week are posted each Friday.

Sign Up for Traffic Alerts on Virginia 511

Don't forget you can get the latest on work zones, accidents and other incidents by visiting 511virginia.org, using the Virginia 511 app, or by calling 511 from any phone in Virginia. Visit the site or app to create and configure your account for alerts.

You can also check out updates for major incidents @511northernvirginia on Twitter.