PLACER/NEVADA/SIERRA COUNTIES – Caltrans is reminding motorists of various lane and ramp closures in five locations along Interstate 80 (I-80) as emergency repairs continue in Placer, Nevada and Sierra counties. Here is the breakdown for next week:
Westbound I-80
-
Location 5 - Between Floriston and Hinton Road, lane closures will be in place around the clock beginning 9 p.m. Tuesday, May 28 through 10 a.m. Friday, May 31.
-
Location 4 – Between State Route 89 and Donner Pass Road, lane closures will be in place from 7 a.m. to 5 p.m. Wednesday, May 29 and Thursday, May 30.
-
Location 3 - Between Rainbow and Cisco Grove, lane closures will be in place from 7 a.m. to 7 p.m. Wednesday, May 29 and Thursday, May 30.
-
Location 2 - Between Emigrant Gap and Nyack, lane closures will be in place from 7 a.m. to 7 p.m. Wednesday, May 29 and Thursday, May 30. Additional work is also scheduled from 4 a.m. to 1 p.m. Friday, May 31.
- Location 1 - No work anticipated next week.
Eastbound I-80
-
Location 1 - No work anticipated next week.
- Location 2
-
Between Drum Forebay and Blue Canyon, lane closures will be in place from 7 p.m. to 7 a.m. Wednesday, May 29 through Friday, May 31. Work is scheduled to end for the week at 7 a.m. Saturday, June 1.
-
Between Blue Canyon and Emigrant Gap, lane closures will be in place from 7 a.m. to 7 p.m. Wednesday, May 29 and Thursday, May 30. Additional work is scheduled from 3 a.m. to noon Friday, May 31.
-
Location 3 - Between Big Bend and Rainbow, lane closures will be in place from 7 a.m. to 7 p.m. Wednesday, May 29 and Thursday, May 30.
- Location 4
-
Between Kingvale and Soda Springs, lane closures will be in place from 7 a.m. to 5 p.m. Wednesday, May 29 and Thursday, May 30.
-
Between Donner Lake Interchange and State Route 89, lane closures will be in place from 7 a.m. to 5 p.m. Wednesday, May 29 and Thursday, May 30.
- Location 5 - No work anticipated next week.
Additional night work is scheduled next week along I-80 between Troy and Soda Springs as crews begin construction on the $97.2 million Soda Springs Pavement Rehabilitation Project. Various lane closures will be in place eastbound and westbound 9 p.m. to 9 a.m. Tuesday, May 28 through Thursday, May 30. Work is scheduled to end for the week at 9 a.m. Friday, May 31.
Motorists will experience delays and are encouraged to factor in additional travel times along the I-80 corridor. The schedule is subject to change or be delayed due to weather, availability of materials or other unexpected events.
Caltrans performed an extensive field review of the I-80 corridor in 2023 and found an unprecedented amount of damage. Several areas exhibited moderate to high levels of rutting due to chain wear and required immediate repair. Five emergency contracts were executed in 2023 for the repairs, along with an additional four emergency contracts in 2024, totaling $107.4 million. The primary contractors are Teichert, Vanguard Construction, Dees Burke Engineering Constructors, Granite Construction, and Q&D Construction.
|