Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
- Completed noise barrier foundation drilling and started post and panel installation along eastbound Route 7 between Bishopsgate Way and Markell Court.
- Continued drilling noise barrier foundations and started post and panel installation along eastbound Route 7 between Utterback Store Road and Bishopsgate Way.
- Finished final surface paving for the left and center lanes on westbound Route 7 between Colvin Run Road (west) and Amanda Drive, and on eastbound Route 7 between Bishopsgate Way and Delta Glen Court.
- Finished final surface paving for the right lane on eastbound Route 7 between Bishopsgate Way and Baron Cameron Avenue.
Area 2: Baron Cameron Avenue Intersection
- Completed curb installation at the Baron Cameron Avenue intersection.
Area 3: Difficult Run Area (Colvin Forest Drive to Faulkner Drive
- Poured the concrete barrier between the westbound Route 7 travel lanes and the shared use path on the Difficult Run bridge, completing all bridge construction over Difficult Run.
Area 4: Faulkner Drive to Jarrett Valley Drive
- Completed final surface paving for the left and center lanes on eastbound Route 7 between Trap Road and Jarrett Valley Drive.
- Continued storm sewer installation at Wolftrap Run Road.
-
Placed intermediate asphalt for Stage 3B between Difficult Run and Lyons Street, and between Towlston Road and Lucky Estates Drive.
Project-Wide
- Third-party utility relocation activities are ongoing.
- Continued fence installation at stormwater management ponds.
- Continued grading, placement of stone and paving for the shared-use paths.