In March, crews continued construction activities along the corridor:
Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
- Continued construction of the shared-use paths along Route 7.
- Drilled noise barrier foundations along westbound Route 7 near Springvale Road.
Area 2: Baron Cameron Intersection
- Continued construction of the improvements on Baron Cameron Avenue between Route 7 and Hunter Gate Way.
Area 3: Difficult Run Area (Colvin Forest Drive to Faulkner Drive)
- Completed storm sewer installation for Stage 3A between the east end of Colvin Run Road and Faulkner Drive.
- Placed concrete for the deck of the new Difficult Run bridge on westbound Route 7.
Area 4: Faulkner Drive to Jarrett Valley Drive
- Installed noise barrier panels along eastbound Route 7 between Towlston Road and Jill's House.
- Completed drilling for the foundations of the retaining wall along westbound Route 7 near Faulkner Drive.
- Completed storm sewer installation for Stage 3A between Towlston Road and Lucky Estates Drive.
- Continued earth-moving activities, grading, and placement of soil cement along eastbound Route 7 between Towlston Road and Lucky Estates Drive.
- Began base asphalt paving and curb construction along eastbound Route 7 between Beulah Road and Atwood Road, and between Lucky Estates Drive and Lewinsville Road.
- Completed rough excavation for the stormwater management pond between Wolftrap Run Road and Jill's House.
|