495 NEXT NEWS

I-495 Express Lanes Northern Extension (495 NEXT) Project Update

Issue 18 | Summer 2024

In This Issue...


  • Georgetown Pike Travel Lanes Shifted to New Northern Portion of Bridge
  • Paving the Way: New Beltway Lanes Starting to Take Shape with Initial Paving
  • Under the Hard Hat Profile
  • Drop-In Public Hours Continue Through September
  • Transurban's 495 NEXT Community Grant Program

Georgetown Pike Travel Lanes Shifted to New Northern Portion of Bridge 

All lanes on the Georgetown Pike Bridge over I-495 in McLean were shifted to a new northern portion of the bridge over the weekend of August 23-26. The work was completed, and all lanes on the Georgetown Pike Bridge and ramps connecting to I-495 were reopened ahead of schedule on Sunday afternoon, August 25. The 495 NEXT project team thanks motorists for their help by adjusting travel plans and “staying away” during the weekend-long operation. 


Prior to the weekend traffic shift, a new turn lane/ramp from westbound Georgetown Pike to northbound I-495 was opened to traffic. This lane/ramp is providing drivers more gradual and smoother access in this busy interchange area.

Georgetown Pike Bridge after the recently completed traffic shift on weekend of August 23-26 (August 2024).

What Happens Next:


In early-to-mid September, crews will begin demolishing the existing southern portion of Georgetown Pike Bridge. Following this demolition, crews will construct a new southern portion of the bridge, which is expected to open in mid-2025. Once the new southern portion of the bridge is built, crews will implement another traffic shift to put traffic into its final configuration on the completed, final bridge. The overall new Georgetown Pike Bridge is expected to open in late 2025. 

Paving the Way: New Beltway Lanes Starting to Take Shape with Initial Paving

Following two-plus years of preparatory work – including earth work, installing new drainage, relocating utilities, removing noise walls to make room for new, upgraded noise walls, and bridge foundation work – the new outer lanes of the Beltway began to take shape in June with initial paving occurring on northbound I-495 between Old Dominion Drive and Georgetown Pike. 


Following paving, lane and shoulder markings will be installed. Paving also has been underway for ramps to and from the George Washington Memorial Parkway and the ramp from westbound Georgetown Pike to northbound I-495. 


The new outer lanes are planned to be completed – and start carrying traffic – in late 2024 or early 2025, with traffic being switched onto the new lanes in phases, as the various sections are completed. Switching traffic onto the outer lanes will allow crews to begin building the new express lanes in the footprint of the existing Beltway. The project remains on track with the two-and-a-half mile express lanes extension from Tysons to the George Washington Memorial Parkway scheduled to open in late 2025.

Asphalt being installed for the new outside lanes of northbound I-495 (July 2024).

Under the Hard Hat Profile

Jim Compton

Senior Superintendent

Lane Construction


Q: How would you describe your role on 495 NEXT supervising Maintenance of Traffic (MOT)? 

A: My role is to provide the overall management for how lane closures are implemented, making sure we’re coordinating correctly with other entities, and that our closures are done to code. I also use my experience to help provide guidance on how our closures should be designed to minimize impact for the construction team and the motoring public.


Q: What is the importance of MOT on projects of this size and impact? 


A: First and foremost, it’s the safety of the public and the workers on site in general. The importance is also to get the worksite vehicles in and out efficiently, to help maintain the schedule and ensure we’re on time for completion. 


Q: In what ways has 495 NEXT been unique compared to other projects you’ve supported in your career?


A: The uniqueness of this project is that even though it is only 2.5 miles in length, it’s challenging to provide all the MOT support needed in that short span. There are several entities with whom we must facilitate constant coordination with. We also have significant and extensive detours that have to be implemented for the construction of this project where we need to balance the impact on traffic with safety and productivity. 


Q: What have you enjoyed most about working on 495 NEXT? 


A: The challenge of the complexity of the work, not only from an MOT standpoint but also a construction standpoint. Also, the chance to mentor the younger workers on our team. I’ve worked for Lane for over 33 years, and I’ve seen a lot of things that have given me the ability to share knowledge and advice with our young engineers. 


Q: Are there any defining moments that have helped you progress to your current role?


A: The first is the phone call I got from my father-in-law who recruited me to Lane in 1991. Another was transferring from Texas to work on the 395 project to take over as the MOT manager, which was a new role for me. The last was deciding to take on the 495 project over other opportunities with Lane to stay close to my family and help build something for my community. The defining factor has always been family. 


Q: What’s the best piece of advice you have for someone interested in pursuing a career in construction management? 


A: Don’t let anyone outwork you. Hard work gets rewarded. Learn not only your role, but everyone else’s you work with, and observe it in the field. As a construction manager, always remember it’s “we” not “I,” and give credit where credit is due. We all succeed together. Finally, our business is based around people. Know your people, know their limitations, and try to make the most of those limitations. If you maximize everyone on your team’s potential, that’s what makes a great construction manager.

495 NEXT Public Hours


VDOT and its 495 NEXT project partners continue to hold drop-in public hours through September to provide the public opportunities to interact with project staff, learn more and ask questions about the project. No appointment is necessary. Upcoming dates and details are:

  • Thursday, September 19 | 4-6 p.m.
  • Thursday, September 26 | 1-3 p.m.

Join In-Person

McLean Governmental Center

1437 Balls Hill Road

McLean, VA 22101

Join Virtually

Visit 495NEXT.vdot.virginia.gov for links to individual sessions and details on how to participate virtually.

Email 495NorthernExtension@vdot.virginia.gov or call 703-691-6715with any questions.

Accepting Applications for Transurban's 495 NEXT Community Grant Program

Explore the latest community initiatives supported by Transurban, private partner to VDOT on the 495 NEXT project and operator of the express lanes. Through its grant programs, Transurban actively seeks opportunities to directly support neighborhoods within the 495 NEXT project corridor. Listed below are the summer 2024 grant recipients:


  • Fairfax Symphony Orchestra – Funds transportation for approximately 2,000 third through sixth graders in Fairfax County to participate in the Link Up! musical education program


  • McLean Revitalization Corporation – Funds technology equipment needed to host McLean Movie Night to continue increasing economic vitality and build a sense a community in downtown McLean


Groups dedicated to improving communities along the 495 NEXT corridor are invited to submit applications for Transurban's 495 NEXT Community Grant program. 


The next deadline to apply for a community grant is September 30, 2024. 


Click here to learn more about Transurban’s Express Lanes Community Grant programs and how to apply.

Learn More About the Project


Check out www.495NEXT.VDOT.Virginia.gov for additional information.


Sign up here to receive project email updates.



laptop_495EX website.png

Questions?

Email: 495NorthernExtension@vdot.virginia.gov

Call: Construction Inquiry Line, 703-592-6430

Virginia Department of Transportation, Michelle Holland, 703-586-0487

Transurban, Amanda Allen, 571-249-8784

Lane Construction, John Undeland, 703-785-3461

Facebook  Instagram  X  YouTube