Phase II: Temporary Traffic Pattern Changes
(Wednesday, May 15 – Friday, May 17)
Temporary Traffic Pattern Changes
-
41 Street westbound between Pine Tree Drive and Indian Creek Drive will be reduced to one lane.
-
41 Street from Indian Creek Drive to the east street end (Beachwalk) will be closed to all traffic.
-
Collins Avenue at 41 Street intersection will be closed to all traffic. See posted detour signs.
-
Indian Creek Drive from 40 to 41 Streets will be reduced to one lane northbound and one lane southbound.
-
Indian Creek Drive southbound from 41 to 44 Streets will be reduced to two lanes: one right turn only lane and one straight lane.
Timeline
This project is expected to conclude in September 2024. Work hours are Monday–Friday, from 7 a.m. to 6 p.m., and on Saturdays from 9 a.m. to 4 p.m. Due to the nature of this operation and heavy machinery, a 24-hour lane closure will be in effect.
Please note that pull back operations are continuous and may occur outside of the stated working hours to ensure timely completion of the project.
Please know that this schedule may change due to weather or unforeseen circumstances.
|