Crane Lift: 17 East Erie:
On Monday, July 15, from 8am to 5pm, there will be a crane lift at 17 East Erie Street. During the lift, the following will be closed:
- Sidewalk on the south side of Erie, between State and Wabash
- Curb and one traffic lane on the south side of Erie, between State and Wabash
There will be one westbound lane of traffic always open during the lift.
Filmings
Riverwalk & Navy Pier Filming
On Monday, July 15th, a commercial will be filming exterior scenes at the Chicago Riverwalk & Navy Pier. During filming, parking will be prohibited at the following locations:
- North Side of Grand from Streeter Dr to Dusable Lake Shore Dr (Monday, July 15th, from 8:00AM to 2:00PM)
- West Side of Clark St from Wacker Dr to Lake St (Monday, July 15th, from 8:00AM to 2:00PM)
If you have any questions, concerns or special needs, please contact: Liz Amdahl, 505-787-3076.
321 N Clark Filming
On Tuesday, July 16th, & Wednesday, July 17th, there will be filming of exterior scenes at the Chicago River & 321 N Clark St. During filming, parking will be prohibited at the following locations:
- East Side of Clark St from Kinzie south to the Chicago River (Tuesday, July 16th, from 8:00PM to 2:00AM)
- East Side of Clark St from Wacker Dr to Lake St (Tuesday, July 16th, from 8:00PM to 2:00AM)
- East Side of Clark St from Kinzie south to the Chicago River (Wednesday, Jily 17th, from 2:00PM to 2:00AM)
- South Side of Carroll St from Clark St west 60ft (Wednesday, Jily 17th, from 2:00PM to 2:00AM)
Please note there will be intermittent traffic control on Dearborn St Bridge & Clark St Bridge on Tuesday, June 16th at 10PM through Wednesday, June 17th at 2AM.
If you have any questions, concerns or special needs, PLEASE CONTACT: Liz Amdahl, 505.787.3076
Gold Coast Water Main Project Update
Mon ~ Fri ( 7/15-7/19)
- Monday, July 15: 41 East Oak service transfer (water service interrupted during service transfer
- Monday, July 15: 54-56 East Oak Street final connection and catch basin installation
- Tuesday, July 16: 130 East Oak Street install source connection and pressure test
- Wednesday, July 17 to Friday, July 19: Chlorination, water quality test and approval of service transfers from remaining ½ east block of Oak Street.
Helicopter Lift - 333 W Wacker Drive
Midwest Helicopter was hired to lift HVAC units onto the roof of 333 W Wacker Drive. The lift is scheduled to occur on Saturday, July 20, from 9am to 11am. During the lift, the following will be closed to vehicular and pedestrian traffic:
- Wacker Drive, between Franklin and Lake
Upcoming CDOT Bridge Work - Michigan Avenue Bridge Sidewalk Repairs - SE Corner
CDOT crews are scheduled to perform the sidewalk repair work at the Michigan Avenue Bascule Bridge over the Main Branch of the Chicago River. These repairs are similar in scope to the sidewalk repairs completed on the southwest corner of this bridge in March.
Scope of Work:
The project consists of performing the following repairs: SE sidewalk concrete repairs.
Construction Schedule:
7:00 am - 3:00 pm, Monday thru Friday, from Monday, July 8th until Friday, July 19th.
Traffic Impact during Construction:
- Full closure of East sidewalk at all times.
- A single Northbound vehicular lane closure adjacent to the sidewalk being worked on during working hours ONLY, and will go into place after rush hour.
225 W Randolph Street Vaulted Sidewalk Repair
The owner of 225 W Randolph Street will be rebuilding the following vaulted sidewalks adjacent to the property:
- South side of Randolph, from Franklin to the east end of the building
- West side of Franklin, from Randolph to the south end of the building
This project will begin on Monday, July 8th and will take approximately 3 weeks to rebuild each sidewalk. Pedestrians will be pushed to the opposite side of the street during construction. Click here to view their site plan.
Added Bus Stops
Due to the Expanded Outdoor Dining program, the following bus stops will be implemented, effective on Friday, May 24, 2024, at 3:00 pm until Thursday, October 31, 2024 or completion.
Clark at Kinzie (southbound, nearside)—Temporary bus stop elimination
Stop ID Number: 1861
Route Stopping: #22 – Clark
LaSalle at Grand (southbound, farside)—Temporary bus stop route added onto existing bus stop
Stop ID Number: 4961
Route Stopping: #22– Clark, #156 - LaSalle
LaSalle at Hubbard (southbound, farside)—Temporary bus stop route added onto existing bus stop
Stop ID Number: 4962
Route Stopping: #22– Clark, #156 - LaSalle
LaSalle at 320 North (southbound, farside)—Temporary bus stop route added onto existing bus stop
Stop ID Number: 4963
Route Stopping: #22– Clark, #156 - LaSalle
Protected Bike Lane Installation: East Side of Clark, from Oak to Grand
The Chicago Department of Transportation (CDOT) is expanding its protected bike lane network throughout the City. They have decided to install a southbound protected bike lane on the east side of North Clark Street, between West Oak Street and West Grand Avenue. This bike lane will connect to the westbound bike lane on the north side of West Grand Avenue.
CDOT's Scope of Work:
- Swap the location of the existing bike lane and parking lane. The bike lane will be adjacent to the curb and the parking lane will be between a lane of traffic and the bike lane.
- Install bicycle signals (select intersections).
- Install pedestrian bump-outs/refuge space.
Please click here to review CDOT's site plans. Work is currently underway.
Demolition Project: 720 North Wells Street / 207 West Superior Street
Milburn Demolition concluded its demolition of 207 West Superior Street and began demolition of 720 North Wells Street last week. Work hours will remain Monday - Friday, from 8am to 5pm.
The following will be closed throughout the project:
- 40 feet of the north/south alley on the south side of West Superior Street, between North Franklin Street and North Wells Street
- Sidewalk and curb lane on the south side of West Superior Street, between North Wells Street and North Franklin Street
- Sidewalk and curb lane on the west side of North Wells Street, from West Superior Street to a point 48 feet south thereof.
The bike lane on the west side of North Wells Street will remain open throughout the project. Demolition is expected to be completed by August 1, 2024 (weather dependent).
Franklin Street Bridge Project
CDOT crews began sidewalk replacement and selective roadway grating replacement at the Franklin Avenue Bascule Bridge over the Main Branch of the Chicago River.
Scope of Work:
The project consists of performing the following repairs: replacement of bridge sidewalk with fiberglass sidewalk panels, selective roadway grating panels replacement.
Construction Schedule:
7:00 am - 3:00 pm, Monday thru Friday, from Monday, March 18th until Friday, August 30th. End date is tentative, contingent upon expected Central Business District Moratoriums.
Traffic Impact during Construction:
- Full closure of one sidewalk at all times.
- A single vehicular lane closure adjacent to the sidewalk being worked on at all times.
- One northbound though lane and northbound bike lane will remain open throughout during sidewalk repairs.
CDOT Construction: Pin & Link Plate Assembly and Expansion Joints
The Department of Transportation will begin a project to replace pin and link plate assemblies and expansion joints associated with the bridge structures of upper and intermediate Columbus Dr., Randolph St., and Stetson Ave. Pin and link plate assembly work will be performed from the underside of the bridge decks while expansion joint replacements will occur from above. The work began in November 2023 and will progress to completion (anticipated Fall 2024).
Work is to start along upper, intermediate, and lower levels of the following roadways:
- N. Columbus Drive between E. Wacker Drive and E. Randolph Street
- E. Randolph Street between N. Michigan Avenue and N. Field Boulevard
- N. Stetson Avenue between E. Wacker Drive and E. Lake Street
During construction, portions of these bridge structures will be barricaded off to prohibit vehicles and pedestrians directly over the active work.
- Vehicles will be shifted and/or detoured to allow the work to progress.
- The sidewalk on at least one side of the roadway and crosswalks at roadway intersections will remain open for pedestrians.
- Coordination of temporary access restriction may be required with private properties directly adjacent to the project.
State & Lake Utility Relocations
Utility companies began relocating utilities in advance of the State and Lake CTA project. Train services will not be disrupted during utility relocations.
At least 1 lane of traffic will remain open (1 lane each direction on State St) at all times, but other driving and parking lanes may be closed.
Construction equipment and materials will be stored on the street, including during time periods between active work. Work will primarily occur 9:00 AM to 4:00 PM on weekdays and 8:00 AM to 8:00 PM on Saturdays, but there will be limited work during nights. Utility companies are aware of and required to abide by the Chicago noise ordinance, which limits noisy work during overnight hours.
Kennedy Expressway Bridge Rehabilitation
In 2023, IDOT began rehabilitating the Kennedy Expressway (Interstate 90/94), from the Edens Expressway (I-94) junction to Ohio Street.
The estimated $150 million project consists of rehabilitating 36 bridges and the Reversible Lane Access Control system, replacing overhead sign structures, installing new signage and modernized LED lights, pavement patching, and structural painting. Additionally, Hubbard’s Cave, from Grand Avenue to Wayman Street, will be painted and new LED lighting installed.
The work will take place over three consecutive construction seasons, broken down into the following stages:
-
2023 – Inbound Kennedy: Click here for stage 1 fact sheet.
-
2024 – Reversible Express Lanes: Click here for stage 2 fact sheet.
-
2025 – Outbound Kennedy: Click here for stage 3 fact sheet.
The Kennedy Expressway officially opened in November 1960, with the last major rehabilitation completed in 1994. The project will improve safety, traffic flow and reliability for the more than 275,000 motorists who use the expressway each day.
Click here for a project overview.
Click here for a FAQ
Click here to see photos and videos of the project.
|