2024 Mill & Overlay and Smithtown Road Drainage Improvements Project

Work on Phase 3 Streets will begin the week of July 15th. Phase 3 Streets include Church Road, Murray Street/Court and Lilac Lane. Please note that with the start of construction on Phase 3 Streets, there may be times when you must wait for crews in order to access your driveway or the roadway. The construction schedule for next two weeks is as follows: 

 

Upcoming week (Week of July 15)

  • Seeding and landscape restoration for Phase 2 Streets.
  • Church Road storm sewer installation. This work will begin on July 18th and is planned to be completed on July 19th. There will be limited access into the cul-de-sac when this work is taking place.


Following week (Week of July 22)

  • Concrete and asphalt removals for Phase 3 Streets.
  • Storm sewer installation on Murray Street and at the Cardinal Avenue intersection. There will be limited access at the Murray Street/Cardinal Avenue intersection when this work takes place. More information will be given when the dates of this work are confirmed.


Project Information & Reminders

  • This work is weather pending and will be performed the following day if rain delays occur.
  • Construction working hours are 7 AM - 7 PM.
  • All roads under construction will be open to local traffic only. There may be times when you must wait for construction personnel in order to access your road/driveway. Please be patient as crews work to complete construction activities.
  • Please watch small children and animals carefully around all construction activities.

Resident Project Representative

For construction related issues, please contact the Resident Project Representative:

  • Sophia Heuer (320) 510-0721
Visit the Project Page
Facebook  X  Instagram  Web

You are receiving this email because you are signed up for General Road Construction and previous Mill & Overlay Projects updates. To unsubscribe to all Shorewood emails, please select "Unsubscribe" below. To unsubscribe from this email only, or to update additional email requests, select "Update Profile". For assistance, contact the city at 952.960.7900, or reply to this email.