The construction schedule for the next two weeks are as follows for Phase 2 Streets (Spruce Hill Court, Boulder Circle, and the following intersections off Smithtown Road: Virginia Cove, Boulder Circle, Howard's Point Road, Cajed Lane, Fairway Drive, Ayrshire Lane, Star Lane, Christopher Road):
June 18-21:
- Concrete curb pouring for spot repair locations. This work will start on Spruce Hill Court on Tuesday, then the crews will move to the locations off Smithtown and end with Boulder Circle.
June 24-28:
- Asphalt patching in front of spot curb repair locations and driveways.
- Milling for Phase 2 streets.
- Mainline bituminous paving for Phase 2 streets.
|