The construction schedule for the week of June 3rd is as follows for Phase 1 Streets (Whitney Circle, Chestnut Court, Maple Street, Bracketts Road and Oakview Court):
- June 3: Mainline bituminous level course patching, weather pending. This involves paving a thin layer of asphalt over the existing pavement in certain areas to improve surface irregularities or lack of an existing pavement section.
- June 4: No construction work.
- June 5: No construction work.
- June 6 & 7: Mainline bituminous paving begins at 12 pm on June 6. The Phase 1 Streets will be paved in the following order: Whitney Circle, Chestnut Court, Bracketts Road, Oakview Court, Maple Street. Please avoid street parking in order for construction activities to take place. There will be limited driveway access. If rain delays occur, this work will be performed the week of June 10th.
Concrete curb repairs, sanitary and storm sewer casting adjustments, irrigation/dog fence repairs, driveway paving, and seeding have been completed for Phase 1 Streets.
|