The construction schedule for the Week of May 13 is as follows:
*Please note: if weather issues arise, the work will be performed the following day
May 13: Construction began with concrete curb and driveway removals on Whitney Circle, Chestnut Court, Oakview Court, and Bracketts Road.
May 14: Concrete curb pouring on Whitney Circle, Chestnut Court, Oakview Court and Bracketts Road is scheduled.
There is a 7-day cure time for the concrete to harden. If the concrete curb has been removed in front of your driveway, access to your driveway will be restored after the 7 days. Contact the resident project representative for questions on access and parking.
May 15-17: Potential topsoil replacement behind the curb removal locations on Whitney Circle, Chestnut Court, Oakview Court and Bracketts Road.
|