CONSTRUCTION ACTIVITIES:
Next week, during the daytime hours, independent utility companies will be on-site conducting utility relocations in preparation for the start of construction.
Crews will be on-site Monday through Friday, between 7 a.m. and 7 p.m., to install erosion prevention and sediment control measures off the roadway throughout the project area. There is also potential for crews to install silt fencing off of the roadway along U.S. 7 within the project limits.
Nighttime construction activities along U.S. 7, starting just south of the Shell Gas Station/Simon’s Chimney Corner Store and extending north to Wiley Road, are anticipated to begin at the end of May/early June of 2024. This work will take place Sunday through Thursday between the hours of 8 PM and 6 AM. Additional information and traffic impacts will be provided closer to the start of construction.
|